Program Logic

Four interconnected workstreams

The program runs as four parallel tracks, coordinated by a continuous governance layer.

Project Governance & Prioritization

Continuous prioritization, review cadence, approval management, and coordination across all four workstreams for the full 24 weeks.

These four workstreams do not run separately. They overlap by design: interim support keeps the business active while strategy is defined, brand decisions release the content system, content and course data unlock the website, and the website consumes the outputs of all three. Each track provides inputs the others depend on, and every handover point is planned rather than incidental.

Interactive Roadmap

The 24-week program at a glance

Hover a bar for its timing, dependencies, and expected outcome. Select one to open the full detail.

Filter
Phase 01Weeks 1–4

Stabilization & Discovery

  • Project Governance & Prioritization

    Weeks 1–24 · Governance

  • Interim Design & Business Support

    Weeks 1–8 · Interim Support

  • Brand and Communication Audit

    Weeks 1–4 · Brand

  • Content and Course-Data Normalization

    Weeks 1–10 · Content & Assets

  • Brand Strategy and Architecture

    Weeks 2–8 · Brand

  • Website Audit and Content Inventory

    Weeks 4–7 · Website

Week 4 milestone

Audit and Priorities Aligned

Audit findings reviewed and the support backlog prioritised.

Phase 02Weeks 5–8

Strategic Foundation

  • Project Governance & Prioritization

    Weeks 1–24 · Governance

  • Interim Design & Business Support

    Weeks 1–8 · Interim Support

  • Content and Course-Data Normalization

    Weeks 1–10 · Content & Assets

  • Brand Strategy and Architecture

    Weeks 2–8 · Brand

  • Visual Identity Enhancement

    Weeks 6–12 · Brand

  • Corporate and Academy Content Development

    Weeks 5–14 · Content & Assets

  • Website Audit and Content Inventory

    Weeks 4–7 · Website

  • Website Strategy, Sitemap, and UX

    Weeks 7–12 · Website

Week 8 milestone

Interim Support Ends / Strategy Approved

Brand platform approved; interim period closes and work moves onto the approved direction.

Phase 03Weeks 9–12

Identity & Content System

  • Project Governance & Prioritization

    Weeks 1–24 · Governance

  • Content and Course-Data Normalization

    Weeks 1–10 · Content & Assets

  • Visual Identity Enhancement

    Weeks 6–12 · Brand

  • Brand Guidelines and Master Templates

    Weeks 11–16 · Brand

  • Corporate and Academy Content Development

    Weeks 5–14 · Content & Assets

  • Corporate Profile and Academy Profile

    Weeks 9–16 · Content & Assets

  • Course Catalog and Commercial Materials

    Weeks 10–18 · Content & Assets

  • Website Strategy, Sitemap, and UX

    Weeks 7–12 · Website

  • Website Content and UI Design

    Weeks 11–17 · Website

Week 12 milestone

Visual Identity Approved

Enhanced visual system signed off and released to downstream work.

Phase 04Weeks 13–16

Brand Toolkit & Priority Assets

  • Project Governance & Prioritization

    Weeks 1–24 · Governance

  • Brand Guidelines and Master Templates

    Weeks 11–16 · Brand

  • Corporate and Academy Content Development

    Weeks 5–14 · Content & Assets

  • Corporate Profile and Academy Profile

    Weeks 9–16 · Content & Assets

  • Course Catalog and Commercial Materials

    Weeks 10–18 · Content & Assets

  • Website Content and UI Design

    Weeks 11–17 · Website

  • Website Development and Integrations

    Weeks 16–22 · Website

  • Wider Collateral and Brand Rollout

    Weeks 15–24 · Content & Assets

Week 16 milestone

Brand Toolkit and Core Profiles Ready

Guidelines, master templates, and the two core profiles complete.

Phase 05Weeks 17–20

Website & Rollout

  • Project Governance & Prioritization

    Weeks 1–24 · Governance

  • Course Catalog and Commercial Materials

    Weeks 10–18 · Content & Assets

  • Website Content and UI Design

    Weeks 11–17 · Website

  • Website Development and Integrations

    Weeks 16–22 · Website

  • Wider Collateral and Brand Rollout

    Weeks 15–24 · Content & Assets

Week 20 milestone

Website Build Review

Development build reviewed against the approved design and content.

Phase 06Weeks 21–24

Launch & Transition

  • Project Governance & Prioritization

    Weeks 1–24 · Governance

  • Website Development and Integrations

    Weeks 16–22 · Website

  • Website Testing and Launch

    Weeks 21–24 · Website

  • Wider Collateral and Brand Rollout

    Weeks 15–24 · Content & Assets

Week 24 milestone

Website Launch and Core Rollout

Website live and the core brand ecosystem handed over.

Six Strategic Phases

A sequenced path from stabilization to launch

Each phase closes with a defined set of outcomes that release the next stage of work.

Critical Intersections

What each decision releases

A small number of approvals govern the pace of the whole program. Each one unlocks a defined chain of downstream work.

Core Asset Ecosystem

A modular set of communication assets

Separating the assets keeps each document short, purposeful, and independently updatable.

Governance and Planning Notes

How the plan is intended to be run

These principles govern sequencing, approvals, and the relationship between interim work and the enhanced brand system.